Estimate concrete volume for repeated identical rectangular footing runs using one run’s length, width, depth, count, and waste allowance.

Use feet/inches or metres/centimetres for footing runs and review the cubic-yard or cubic-metre volume with the engineered plan.

IMPERIAL + METRIC · LIVE CALCULATION
CALCULATE
FOOTING CONCRETE VOLUME1.74 yd³

1 footing run with 10% waste. The entered dimensions describe one rectangular run; count multiplies that entire run before waste is added.

BREAKDOWN
Unadjusted volume1.58 yd³
Footing count1
Order quantity1.74 yd³
WHEN THIS TOOL HELPS

Total repeated rectangular footing runs.

Use this takeoff after footing dimensions have been specified by an appropriate plan or professional. Enter the length of one run and use count only for identical runs.

Group footings by dimensions and calculate each group separately. This avoids applying one width or depth to unlike strips, pads, or grade beams.

CHOOSING THE RIGHT CONCRETE TOOL

Match the estimate to the purchasing decision.

This calculator multiplies one identical rectangular footing run by a whole-number count. It estimates concrete only and must not be used to choose footing width, depth, reinforcement, bearing area, or foundation design.

HOW IT WORKS

Formula and calculation method.

FormulaOrder volume = one-run length × width × depth × whole-number count × (1 + waste ÷ 100)

Width and depth are converted from inches or centimetres, then multiplied by one run’s length. Count duplicates the entire run, and waste is applied to the combined volume.

WORKED EXAMPLES

Follow realistic concrete takeoffs.

CONTINUOUS STRIP FOOTING

Run length 48 ft; width 16 in; depth 8 in; count 1; waste 10%

Working: 48 × (16 ÷ 12) × (8 ÷ 12) ÷ 27 × 1 × 1.10

Result: 1.74 yd³ to order

Interpretation: Count stays at one because 48 ft is already the complete length of this modeled run.

SIX IDENTICAL SHORT RUNS

Run length 8 ft; width 12 in; depth 8 in; count 6; waste 5%

Working: 8 × 1 × (8 ÷ 12) × 6 ÷ 27 × 1.05

Result: 1.24 yd³ to order

Interpretation: Count six means six separate runs, each 8 ft long with exactly the entered cross-section.

INTERPRETING THE RESULT

Turn the estimate into an order plan.

Confirm whether length means one repeated run or a total combined length; do not multiply both a combined length and its count.

Use separate calculations when any footing has a different width, depth, or shape.

USE IT CAREFULLY

Assumptions and common mistakes.

What the estimate assumes

  • Every counted run is identical.
  • Each footing has a rectangular cross-section.
  • Dimensions come from a valid project specification.
  • Waste applies uniformly to the combined volume.

Mistakes to avoid

  • Using total combined length and also entering multiple runs.
  • Entering a fractional footing count.
  • Using this volume result to select structural dimensions.
  • Including round piers as rectangular footings.
EDGE CASES

Handle unusual concrete plans explicitly.

One continuous run

Enter its total run length and a count of 1.

Different footing sizes

Calculate each identical group separately and add the order volumes.

Round piers

They require cylinder volume and are outside this rectangular-run model.

LIMITATIONS

What this estimate leaves out.

This is not structural or geotechnical design. It excludes soil bearing, frost depth, loads, settlement, reinforcement, code, excavation, keyways, piers, stepped geometry, forms, and inspection requirements.

FAQ

Concrete planning questions.

What does footing count multiply?

It multiplies the complete rectangular run described by the entered length, width, and depth.

Can I use a combined length with count?

Use count 1 if length already combines all identical runs; otherwise you would double-count volume.

Does this calculator size a safe footing?

No. It only estimates volume from dimensions supplied by a valid plan or qualified professional.

Can it calculate round pier footings?

No. Round piers need a cylinder-volume calculation.

How should I handle stepped footings?

Divide them into rectangular segments, avoid overlaps, and calculate each segment group separately.